Projects
Monthly Project Update
2010 Projects |
Status |
| Cedarbrook Subdivision Drainage Improvements | Area 3 complete; pending easements prior to completion of area 2 |
| Fairway Meadows Drainage Improvements | Project complete |
| High Pointe I & II Bridge Deck | Plans under review |
St. Charles Road Round-A-Bout Utility Relocate |
City finalizing design |
| St. Charles Road - High School Project | Paving Battle Drive, week of Oct 10, 2011 |
| Scott Blvd Phase I (City/County) (from Rollins Rd to Brookfield Terrace) | Project complete |
2011 Projects |
|
| Calvert Hill/Boatman Hill/McGee Rd Asphalt Overlay | Construction complete - Fall 2011 |
| Creasy Springs/Roemer Rd Asphalt Overlay | Construction complete - Fall 2011 |
| Fog Seal | Construction complete - Fall 2011 |
| Georgetown Concrete Rehab | Construction complete - Fall 2011 |
| New Haven Rd Asphalt Overlay | Construction complete - Fall 2011 |
| Richland Road Asphalt Overlay | Construction complete - Fall 2011 |
| Sunrise Estates - Phase III | Construction complete - Fall 2011 |
2012 Projects |
|
| Asphalt Rehab Pilot | Developing agreement with engineer |
| Concrete rehab - individual roads, term & supply | Construction to begin week of March 19, 2012 |
| Crack seal | Project complete |
| Creasy Springs Bridge | Awaiting proposals |
| Fairway Meadows subdivision asphalt overlay | Prep work underway |
| Fog Seal | Finalizing contract |
| Gibbs Road - asphalt rehab | Engineering underway |
| High Point Lane Bridge I & II | Construction delayed until fall 2012 |
| Hill Creek Bridge | Awaiting proposals |
| Meyer Industrail Blvd extension road improvements | Revised construction plans to be submitted April 2012 |
| Oakland Gravel asphalt overlay | Prep work underway |
| Old Number 7 asphalt overlay | Projected to begin Fall 2012 |
| Rock Quarry Rd, Gans Rd, & Bearfield Rd asphalt overlay | Constrution to begin 5/14/2012 |
| Rolling Hills Phase 1B | Construction to begin 6/4/2012 |
| St. Charles Alignment study east of high school to Rt Z | Received proposal for traffic study |
| St. Charles Rd Asphalt Overlay | Construction began 5/8/2012 |
| St. Charles round-a-bout | City of Columbia working on final design |
| Shalimar Gardens - concrete rehab | Preparing bid documents |
| Sunrise Estates Phase IV | Preliminary plans complete |
| Trails West stormwater | Projected bid opening May 2012 |
Any questions? Feel free to contact us:
| Boone County Resource Management | |
|
801 E. Walnut Rm. 315 |
(573) 886-4330 Planning |
www.ShowMeBoone.com Boone County, Missouri. 801 East Walnut Columbia, MO 65201 USA